This project was started by others, they had excavated a large hole next to another property owned by the Client.

They had run off after receiving a large sum of money and not doing the work.
We arrived on site in early october, and underpinned the property to the side, as the excavations made it extremely unsafe.
After completing these works, we started laying the new ground bearing slab, and started building sections between two and five meter long.
The weather was very bad and we had to shut the site down on more than one occasion, the rest of the work went smoothly and the Client was more than happy to have his finished basement in february 2021